A town has two lift stations which feed into one in-plant station which then goes to the WWTP. Lift station #1 has three 1,120 gpm pumps with 90% efficiency, two which alternate and the third is a back-up. Lift station #2 also has three pumps operating with the same configuration, but the pumps are 1,000 gpm with 86% efficiency. Both lift stations are 20 feet in diameter and 30 feet deep. Calculate the gpd pumped to the in-plant station from lift station #1 if operated for 16.3 hours and find the total flow to the WWTP in MGD from both lift stations if #2 operates 22.4 hours per day.