Your facility installs an average of 125 lf of 6 inch PVC wastewater main every week. You are required to keep a 12 week reserve supply on hand at all times in case of a major repair. If it takes 4 weeks to obtain a new supply of pipe after an order, what is the minimum inventory required before ordering additional pipe?